menu
arrow_back
PSK-I Valid Exam Simulator | Exam PSK-I Tests
PSK-I Valid Exam Simulator,Exam PSK-I Tests,PSK-I Reliable Exam Questions,PSK-I Valid Dumps Ebook,Valid PSK-I Exam Simulator, PSK-I Valid Exam Simulator | Exam PSK-I Tests

In order to cater to different needs of customers, three versions for PSK-I training materials are available, you can choose the most suitable one in accordance with your own needs. PSK-I PDF version is printable, and if you prefer a hard one, you can choose this version. PSK-I Soft test engine supports MS operating system, and it can install in more than 200 computers. PSK-I Online Test engine is convenient and easy to learn, you can have offline practice if you want. PSK-I Online soft test engine supports all web browsers and it has testing history and performance review, and you can have a general review of what you have learnt before next learning.

The certification exam covers a wide range of topics related to Scrum and Kanban methodologies, including the principles and values of Scrum, the roles and responsibilities of Scrum team members, the Scrum events, the importance of continuous improvement, and the use of Kanban boards in Scrum. The exam also tests the candidate's ability to apply these methodologies in real-world scenarios and to solve complex problems using Scrum and Kanban.

>> PSK-I Valid Exam Simulator <<

Using the PSK-I Exam Questions to get pass

With PSK-I test training materials of LatestCram, you can put away with disorder emotion and clean up them. PSK-I test training materials of LatestCram are the most accurate training materials in the current market. Using it, the passing rate of PSK-I Exam is 100%. Choose LatestCram is equal to choose success.

Scrum Professional Scrum with Kanban level I Sample Questions (Q42-Q47):

NEW QUESTION # 42
When using Kanban in Scrum, a team needs to use which of the following four metrics of flow? (choose the best four answers)

  • A. Lead Time
  • B. Cycle Time
  • C. Throughput
  • D. Cumulative Flow Diagram (CFD)
  • E. Work in Progress (WIP)
  • F. Work Item Age

Answer: B,C,E,F


NEW QUESTION # 43
Scrum Teams using Kanban need to track which four metrics of flow? (choose the best answer)

  • A. Velocity, Lead Time, Cycle Time, Cost.
  • B. Work in Progress (WIP), Velocity, Lead Time, Cycle Time.
  • C. Throughput, Work in Progress (WIP), Velocity, Lead Time.
  • D. Work in Progress (WIP), Work Item Age, Throughput, Cycle Time.

Answer: D


NEW QUESTION # 44
Sprint Planning mainly leverages Throughput in order to create a forecast for the Sprint Backlog.
Which metric would be most relevant to inspect, during Sprint Planning, if you have some items left over from the previous Sprint?

  • A. Lead Time.
  • B. Cycle Time.
  • C. Story Points.
  • D. Work Item Age.
  • E. Work in Progress.

Answer: E


NEW QUESTION # 45
Work Item Age is best described as: (choose the best answer)

  • A. The amount of elapsed time between when a work item "started" and the current time.
  • B. The amount of elapsed time between when a work item entered the Product Backlog and the current time.
  • C. The amount of elapsed time between when a work item entered the Sprint Backlog and the current time.
  • D. The amount of elapsed time between the start of the Sprint and the current time.

Answer: A


NEW QUESTION # 46
True or False: The Sprint Retrospective is the only time in which the Work in Progress (WIP) Limit can change.

  • A. FALSE
  • B. TRUE

Answer: A


NEW QUESTION # 47
......

If you are looking to advance in the fast-paced and technological world, LatestCram is here to help you achieve this aim. LatestCram provides you with the excellent Scrum PSK-I practice exam, which will make your dream come true of passing the Professional Scrum with Kanban level I certification exam on the first attempt.